Attention drivers: Changes coming to I-94 ramps in Racine County as part of WIS 20 project

RACINE COUNTY (WITI) -- The Wisconsin Department of Transportation is scheduled to conduct a traffic switch and begin short-term and long-term closures as part of the WIS 20 Interchange Reconstruction Project.

Friday, March 20 (early morning)

I-94 East (SB) exit ramp to WIS 20 is scheduled to close long-term and is scheduled to reopen mid-summer.


    Friday, March 20 (evening)

    I-94 East (SB) traffic is scheduled to be switched onto I-94 West (northbound).

    I-94 East (SB) entrance ramp from WIS 20 is scheduled to close long-term and is scheduled to reopen late-fall.


      Saturday, March 21 (evening)

      I-94 East (SB) Bridge over WIS 20 is scheduled to be demolished. The demolition will require overnight full closure of WIS 20 under I-94. WIS 20 under I-94 is scheduled to close overnight from 9 p.m. to 8 a.m.


        Additional exit and entrance ramp closures should be expected during the I-94 East (SB) bridge demolition.

        Monday, March 23

        WIS 20 (eastbound) under I-94 will be reduced to one lane from 10 p.m. to 5 a.m.

        Tuesday, March 24

        WIS 20 (westbound) under I-94 will be reduced to one lane from 10 p.m. to 5 a.m.

        All scheduled operations are weather dependent and subject to change. More information about the project can be found at plan94.org.